This is the best NSFW explanation of the Florida bridge collapse

After reading through some of the engineering websites-- and familiarizing myself with the technical language that I don’t have-- I realized they’re were talking about similar things that people have mentioned here.

http://www.eng-tips.com/viewthread.cfm?qid=436595

Here’s a good technical summary:

Basically, the engineering forums are now focusing on truss member #11, and it being strained past capacity, due to less structural redundancy. Conjecture around the failure appears to be the following:

  1. lack of longitudinal PT tendons attaching vertical truss-end #12 to deck
  2. lacked of reinforcement caused by drainpipe and other fittings through the deck and the end of truss #12 (increased chance of stress fractures)
  3. angle of truss #11 at approx. 30-degrees, thus increasing horizontal load strain (compare photos of thicker truss #2 with thinner truss #11)
  4. potential eccentric load (that is, load unevenly applied through truss-members due to asymmetry)
  5. retrofitted ducts in truss #11 for the use of temporary PT tendons to stabilize cantilevering due to SPMTs not being able to maneuver and support the bridge-ends
  6. FDOT redesign request to extend the length of bridge to make room for additional traffic lane
  7. north pier undersized with soft footings due to canal work and delays by Army Corps of Engineers
  8. emphasis on making trusses visually line up with cable-stays, despite increased instability (disregard for design safety in order to aesthetically promote future nearby gentrification projects; early conceptualization had real cable-stays dropped from design but kept for “vibration dampering”)
  9. no redundancy in trusswork (high failure-rate with single row of trusses and no vertical web)
  10. torsion strain (trusswork subject to weak cross-section twisting from wind and over-height truck collisions)
  11. lack of node revolution plates for flexion (joint between truss-ends and top and bottom chords was fixed and brittle)
  12. use of materials lacking ductility (concrete has rapid failure in tension, whereas steel fails more slowly)
  13. change of compression elements without accounting for mid-transport readjustments (tightening compression in non-compression members for transport, but creating tension counter-effects when deck was lowered onto piers without timely readjustment)
  14. push for rapid project completion in order to receive Federal funds
  15. loss of design focus: over-weight, over-budget, under-built, over-promised multi-purpose bridge for social gathering place (not just transit, but superfluous fittings requiring extra cable ducts for circulation fans and wifi with cafe seating over a road with heavy traffic)

And that’s just what I could recall off the top of my head! This was a bad design just waiting to fall down. Period. They’re just lucky it didn’t fall down with hundreds of people on it.

Here’s a truss simulator where you can practice what went wrong:

1 Like